Project & Construction Management

Project & Construction Management

We are handling the entire process of tendering of land, appointment of consultant teams, evaluate tender results and award contracts to contractors. We are a well qualified project manager to oversee the construction site of cost controlled and quality controlled. We have managed well and completed all the projects on time.

Location Land Area sqft GFA sqft Building Cost Construction period Remarks
743 Toa Payoh 44,510 107,640 $10 mil 12 months 8 storey office cum self storage building
615 Toa Payoh 51,500 128,458 10 mil 11 months 8 storey office cum self storage building
25A Changi 60,979 66,000 $6 mil 10 months 2 storey self storage building
15 Changi 64,000 66,000 $9 mil 3 months 4 storey light industrial building (retrofit)
160 Kallang 130,000 310,000 $22 mil 3 months 2 blocks of 4/5 storey light industrial buildings (retrofit)
23 Tampines 215,000 300,000 $45 mil 24 months 2 blocks of 7/8 storey self storage cum design hub (completion Dec 2010)